The Section Of Fifty-Three
Miles From Sarras To Akasha Required Partial Reconstruction.
The section of
thirty-two miles from Akasha to Kosheh must, with the exception of ten
miles of embankment completed in 1885, at once be newly made.
And, finally,
the section from Kosheh to Kerma must be completed before the Nile flood
subsided.
The first duty, therefore, which the Engineer officers had to perform
was the reconstruction of the line from Sarras to Akasha. No trained staff
or skilled workmen were available. The lack of men with technical knowledge
was doubtfully supplied by the enlistment of a 'Railway Battalion' 800
strong. These men were drawn from many tribes and classes. Their only
qualification was capacity and willingness for work. They presented a
motley appearance. Dervish prisoners, released but still wearing their
jibbas, assisted stalwart Egyptians in unloading rails and sleepers.
Dinkas, Shillooks, Jaalin, and Barabras shovelled contentedly together
at the embankments. One hundred civilian Soudanese - chiefly time-expired
soldiers - were also employed; and these, since they were trustworthy
and took an especial pride in their work, soon learned the arts of
spiking rails and sleepers, fishing rails together, and straightening.
To direct and control the labours of these men of varied race and language,
but of equal inexperience, some civilian foremen platelayers were obtained
at high rates of pay from Lower Egypt. These, however, with very few
exceptions were not satisfactory, and they were gradually replaced by
intelligent men of the 'Railway Battalion,' who had learned their trade
as the line progressed.